Drainage works - Clive Street, Range Court Crescent and Green Island Crescent

Published: Wednesday, 4 December 2019 at 2:38:33 PM

As part of the City’s 2019/2020 capital works programme, sections of stormwater infrastructure will be upgraded on Clive Street, Range Court Crescent and Green Island Crescent. 

Works are expected to commence in late January - early February 2020 and expected to be completed by the beginning of March 2020, weather permitting.

A plan of the extent of works can be viewed via the link below:

Extent of works

The City will endeavour to keep disruptions to a minimum and and would appreciate your co-operation in working with on-site staff.  There will be periodical property access issues however the site supervisor will advise affected residences prior to any disruptions.

Construction enquiries should be directed to Austin Rogerson, Senior Civil Engineering Officer, on 6820 3966 during business hours.

Attachment(s)

Map of works

Back to All Items