Albany Surf Life Saving Club Redevelopment


Background

ASLSC provides a highly valued community service for Albany and the Great Southern in the delivery of lifesaving, emergency response, first aid, training and education, and intergenerational sport, recreation, and community events.

In response to the recent infrastructure upgrades within the Middleton Beach Precinct and growing memberships, ASLSC undertook a review of its strategic vision to address several pressing challenges and opportunities affecting its future.

The expansion and redevelopment of the existing club house was identified as a key project to be delivered as part of the ASLSC Strategic Plan to provide:

  • A safer, more efficient, and welcoming community facility:
  • Improved lifesaving and water safety operations; and
  • Increased community engagement through new training and education spaces.

Objectives

The main project objectives are:

  • To address key safety risks related to the access and storage of motorised water safety equipment,
  • To improve the safety, capacity and efficiency of core delivery areas – lifesaving, emergency services, training and education, surf sports and competition, community capacity building;
  • To increase community benefit – improving the quality, capacity and accessibility of community facilities and services; and
  • To assist City of Albany meet growing community demand at Middleton Beach and support the Foreshore and Activity Centre redevelopment goals and community strategic plans.

Scope

The scope of work comprises of:

  • The expansion and separation of motorised water safety equipment and surf sports equipment.
  • A centralised and dedicated life saving hub
  • A new community meeting spaces to support community events and meeting activities. It is envisaged that community groups will be able to book this space at minimal cost – as opposed to booking the whole venue.

The Middleton Beach Public Toilets & Changerooms are located next to the ASLSC building, and do not form part of this project’s scope. There is currently a project underway to refurbish the Middleton Beach Public Toilets & Changerooms. Click here to find out more.

Funding

  • WA Govt - DLGSCI
  • Lotterywest
  • City of Albany
  • Albany Surf Lifesaving Club

Timing

Construction is expected to commence in February 2024 with completion expected to be towards to end of 2024. During construction, the ASLSC building will not be available for use by community user groups. The adjacent public toilets and footpaths may also be unavailable for a short period of time during construction. Temporary facilities will be provided. The community be regularly updated with progress and disruption notices during construction period. 

Albany Surf Life Saving Club Redevelopment Project Profile